King Edward Memorial Hospital

Home/King Edward Memorial Hospital
  • Operating ward
  • Operating wards
  • Operating ward

The works on this project consisted of upgrades and additions to the well known King Edward Memorial Hospital. In particular, the Neonatal and Maternal Foetal Assessment Units that are situated over two levels of the busy hospital.

  • Sector Health
  • Client Department of Treasury & Finance
  • Location Subiaco WA
  • Value $10M
  • Contract Construct Only

The team were required to cut into the existing building and extend post tensioned slabs on Levels 3 and 4 as well as extensive demolition and up-grades to existing areas of the hospital.

The works comprised of two separable portions. Separable portion one was done in three stages with both stages two and three to begin after 32 weeks of possession of site and commencement of stage one.

Separable portion one was completed 57 weeks after possession of site, with the date for practical completion of separable portion two 83 weeks after possession of site.

The works were being done alongside a fully operational hospital so safety, access and environmental consideration were of the utmost concern for our site management team.